BAR Relevant Costs · Updated November 2026

Special Order With Idle Capacity: Which Costs Are Relevant?

With idle capacity, focus on what actually changes if the order is accepted.

Relevant costs

Incremental materials, labor, variable overhead, shipping, customization, and other costs caused by the order are relevant.

Allocated fixed costs

Existing fixed overhead is usually irrelevant if it continues regardless of the decision.

Opportunity cost

If the order uses capacity that could serve another profitable use, lost contribution becomes relevant.

Exam strategy

Build the decision from incremental cash effects, not full unit cost.

The takeaway

With genuine idle capacity, special-order analysis focuses on incremental costs and any opportunity cost, not allocated fixed overhead.

Related Summit resources

FAQ

Is existing fixed overhead always relevant?

No.

When does opportunity cost matter?

When another profitable use of capacity is displaced.

What is the best starting point?

Identify cash flows that change.